Group project timeline template
A free Gantt chart for a group project. Colour each task by who’s doing it, and suddenly everyone knows exactly what they agreed to. It’s amazing what a little colour does for accountability.
How to plan a group project
This one runs about 4 working weeks, which is a typical stretch between “here’s the assignment” and “it’s due Friday”. Change the names in the colour legend to your group’s, adjust the tasks, and share it.
The trick is the links. Some work can happen in parallel (research, the survey, the figures) and some can’t start until something else is done (you can’t combine sections nobody has written). A Gantt chart shows both at once, which is more than a group chat has ever managed.
Where group projects usually go wrong
Sharing the plan with your group
Gantton saves your plans in your own browser, so there’s no account to sign up for. To share, export a view-only HTML file (anyone can open it in a browser), a PDF, or an image to drop in the group chat. Or send them this page and have everyone open the same template.
The plan as text
The same plan in plain text. Copy it and press Ctrl+V in Gantton, or paste it into ChatGPT, Claude or any AI assistant and ask it to fit the plan to your situation first. (More on that in plans from AI assistants.)
Plan: Group project
Colours: Blue = Alex, Green = Sam, Orange = Priya, Purple = Everyone
- Getting started
- First meeting | milestone | purple
- Choose the topic | 2d | after First meeting | purple
- Split up the work | 1d | after Choose the topic | purple
> Write down who does what. Here, in colour. Memories get flexible near deadlines.
- Research
- Background research | 1w | after Split up the work | blue
- Find sources and data | 1w | after Split up the work | green
- Interviews or survey | 1w | after Split up the work | orange
- Building it
- Write the report sections | 1w | after Background research, Find sources and data | blue
- Analyze the survey results | 3d | after Interviews or survey | orange
- Charts and figures | 3d | after Find sources and data | green
- Make the slides | 4d | after Analyze the survey results | orange
- Finishing
- Combine into one document | 2d | after Write the report sections, Charts and figures, Analyze the survey results | green
- Edit for one voice | 2d | after Combine into one document | blue
> So it doesn’t read like three people who’ve never met.
- Rehearse the presentation | 1d | after Make the slides, Edit for one voice | purple
- Hand it in | milestone | after Rehearse the presentation | purple
More templates
One last tip: schedule the project to finish two days before it’s due. It won’t. But it will finish before it’s due.