Wedding planning timeline template

A free Gantt chart for planning a wedding, from the first budget conversation to the thank-you cards. It won’t settle the guest list for you, but it will tell you when it has to be settled.

Wk 1 Wk 5 Wk 9 Wk 13 Wk 17 Wk 21 Wk 25 Wk 29 Wk 33 Wk 37 Wk 41 The big decisions Set the budget Draft the guest list Choose a date and book the venue Book the officiant Vendors Book the photographer Book the caterer Book the music Book flowers and decor Outfits Choose the outfits Outfits made Alterations Guests Wedding website and save-the-d… Book a hotel room block Enjoy being engaged Send invitations RSVPs come in Seating plan The last weeks Final numbers to the caterer Confirm every vendor Rehearsal Wedding day Thank-you cards
UsBookingsVendorsGuestsphasemilestone
Edit this plan in Gantton Opens as your own copy. No account, no signup, and it stays in your browser.

How far ahead should you plan a wedding?

This plan runs about 43 working weeks, a little under a year. Most of the hard deadlines are at the very start (the venue, the photographer, the dress) and at the very end (invitations, RSVPs, final numbers). The middle is mostly waiting, which the plan calls “Enjoy being engaged”.

Planning in less time? It can be done. Shorten the long tasks, pick a less popular date, and be flexible about the venue.

What really sets the schedule

The venue. Almost everything else waits for the date, and the date waits for the venue. Book it first.
The outfits. A made-to-order dress can take four to six months, then alterations. It’s one of the longest tasks in the whole plan and it starts early for a reason.
RSVPs. Invitations usually go out six to eight weeks before the day, and the caterer wants final numbers soon after the RSVPs close. The seating plan sits between the two and is, traditionally, where the drama is.

Why not use a wedding checklist?

Checklists are great until something moves. If the venue only has a date three weeks later than you hoped, a Gantton plan moves the invitations, the RSVPs and the final numbers along with it, because they’re linked. A checklist just sits there, being out of date.

The plan as text

The same plan in plain text. Copy it and press Ctrl+V in Gantton, or paste it into ChatGPT, Claude or any AI assistant and ask it to fit the plan to your situation first. (More on that in plans from AI assistants.)

Plan: Wedding planning
Colours: Green = Us, Purple = Bookings, Orange = Vendors, Navy = Guests
- The big decisions
  - Set the budget | 1w | green
  - Draft the guest list | 2w | after Set the budget | green
  - Choose a date and book the venue | 4w | after Draft the guest list | purple
    > Popular venues book a year or more ahead, especially summer Saturdays. Fridays and off-season months are where the deals hide.
  - Book the officiant | 1w | after Choose a date and book the venue | purple
- Vendors
  - Book the photographer | 2w | after Choose a date and book the venue | purple
  - Book the caterer | 3w | after Choose a date and book the venue | purple
  - Book the music | 2w | after Book the photographer | purple
  - Book flowers and decor | 2w | after Book the caterer | purple
- Outfits
  - Choose the outfits | 4w | after Set the budget | green
  - Outfits made | 4mo | after Choose the outfits | orange
    > Made-to-order dresses often take four to six months. Suits are faster, but tailors have weddings to go to too.
  - Alterations | 6w | after Outfits made | orange
- Guests
  - Wedding website and save-the-dates | 2w | after Choose a date and book the venue | navy
  - Book a hotel room block | 1w | after Choose a date and book the venue | purple
  - Enjoy being engaged | 6mo | after Wedding website and save-the-dates | green
    > Yes, this is a task. Don’t skip it.
  - Send invitations | 1w | after Enjoy being engaged | navy
  - RSVPs come in | 4w | after Send invitations | navy
  - Seating plan | 1w | after RSVPs come in | green
    > Leave extra time for the relatives who can’t sit together. You know the ones.
- The last weeks
  - Final numbers to the caterer | 1d | after Seating plan | orange
  - Confirm every vendor | 3d | after Final numbers to the caterer | green
  - Rehearsal | 1d | after Confirm every vendor, Alterations | green
  - Wedding day | milestone | after Rehearsal | purple
  - Thank-you cards | 3w | after Wedding day | green

More templates

One last tip: assign one task to someone else entirely, then never ask how it’s going. It’s good practice for the day itself.