Kitchen renovation timeline template

A free Gantt chart for a kitchen reno, from the first tape measure to the first meal you cook in it. Open it, change it, and find out exactly how many weeks you’ll be washing dishes in the bathtub.

Wk 1 Wk 3 Wk 5 Wk 7 Wk 9 Wk 11 Wk 13 Wk 15 Design and decisions Measure the kitchen Set the budget Get three contractor quotes Hire the contractor Finalize the layout Choose cabinets and appliances Orders and permits Cabinets made and delivered Appliances delivered Building permit Demolition Set up a temporary kitchen Demolition Rough-ins Plumbing rough-in Electrical rough-in Rough-in inspection Drywall and patching Install Install cabinets Countertop templating Countertop fabrication Install countertops Install appliances Finishing Backsplash Paint and touch-ups Final inspection First meal in the new kitchen
YouContractorDecisions and ordersPermits and inspectionsphasemilestone
Edit this plan in Gantton Opens as your own copy. No account, no signup, and it stays in your browser.

How long does a kitchen renovation take?

This plan comes out at about 15 working weeks, start to finish. Only about half of that involves anyone actually holding a hammer. The rest is quotes, permits, decisions and waiting for things to arrive on a truck.

That’s normal. It’s also the part people leave out of their spreadsheet, which is why the spreadsheet is always wrong.

What really sets the schedule

Cabinets. Custom or semi-custom cabinets often take six to ten weeks. Order them as soon as the layout is final, long before demolition. The plan has them at six weeks; slide that out if your supplier is less optimistic than ours.
Countertops. Stone counters can’t be measured until the cabinets are installed, and then they take a week or two to cut. So there’s a gap in the middle where the kitchen looks almost done and isn’t. Nobody likes this gap. Plan for it anyway.
Inspections. The walls stay open until the rough-in inspection passes. Book it early; the inspector’s calendar is not your calendar.

Why not just do this in Excel?

You can. Lots of people do. Then demolition takes four days instead of three (it will), and you spend an evening dragging forty coloured cells one column to the right.

In Gantton, tasks are linked. When one slips, everything after it moves by itself, and weekends and holidays are skipped. When you’re done, you can still export to Excel, if only for old times’ sake. (More on Gantt charts in Excel.)

The plan as text

The same plan in plain text. Copy it and press Ctrl+V in Gantton, or paste it into ChatGPT, Claude or any AI assistant and ask it to fit the plan to your situation first. (More on that in plans from AI assistants.)

Plan: Kitchen renovation
Colours: Green = You, Orange = Contractor, Purple = Decisions and orders, Navy = Permits and inspections
- Design and decisions
  - Measure the kitchen | 1d | green
  - Set the budget | 2d | green
    > Then add 15%. You’ll find out why behind the first wall you open.
  - Get three contractor quotes | 2w | after Measure the kitchen | green
  - Hire the contractor | milestone | after Get three contractor quotes, Set the budget | purple
  - Finalize the layout | 1w | after Hire the contractor | green
  - Choose cabinets and appliances | 1w | after Finalize the layout | purple
- Orders and permits
  - Cabinets made and delivered | 6w | after Choose cabinets and appliances | purple
    > Six to ten weeks is common. Order before demolition, not after.
  - Appliances delivered | 4w | after Choose cabinets and appliances | purple
  - Building permit | 3w | after Finalize the layout | navy
- Demolition
  - Set up a temporary kitchen | 1d | after Building permit | green
  - Demolition | 3d | after Set up a temporary kitchen | orange
    > If the cabinets are still weeks away, push this back. There’s no prize for living without a kitchen longer.
- Rough-ins
  - Plumbing rough-in | 3d | after Demolition | orange
  - Electrical rough-in | 3d | after Demolition | orange
  - Rough-in inspection | milestone | after Plumbing rough-in, Electrical rough-in | navy
  - Drywall and patching | 4d | after Rough-in inspection | orange
- Install
  - Install cabinets | 4d | after Drywall and patching, Cabinets made and delivered | orange
  - Countertop templating | 1d | after Install cabinets | orange
  - Countertop fabrication | 2w | after Countertop templating | orange
    > The counters can’t be measured until the cabinets are in. That’s the two-week gap everyone forgets.
  - Install countertops | 1d | after Countertop fabrication | orange
  - Install appliances | 2d | after Install countertops, Appliances delivered | orange
- Finishing
  - Backsplash | 3d | after Install countertops | orange
  - Paint and touch-ups | 3d | after Backsplash | green
  - Final inspection | milestone | after Install appliances, Paint and touch-ups | navy
  - First meal in the new kitchen | milestone | after Final inspection | green

More templates

One last tip: whatever the chart says, keep the microwave plugged in somewhere until the very end.