Bathroom renovation timeline template

A free Gantt chart for a bathroom reno: demolition, plumbing, waterproofing, tile, and the long wait for a vanity that was “in stock”. Change it to fit your bathroom and keep it in your browser.

Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7 Wk 8 Wk 9 Wk 10 Planning Measure the bathroom Get contractor quotes Hire the contractor Choose tile and fixtures Vanity and fixtures delivered Plumbing permit Demolition Plan for the other bathroom Demolition Rough-ins Plumbing rough-in Electrical and fan Rough-in inspection Walls and floor Cement board and drywall Waterproofing Floor and wall tile Grout and seal Fixtures and finishing Measure for shower glass Shower glass made Install vanity and toilet Paint Install shower glass Final plumbing inspection First uninterrupted shower
YouContractorDecisions and ordersPermits and inspectionsphasemilestone
Edit this plan in Gantton Opens as your own copy. No account, no signup, and it stays in your browser.

How long does a bathroom renovation take?

This plan runs about 9 working weeks. The room is small, but the list of trades isn’t: a plumber, an electrician, a tiler, maybe a glass company, and an inspector who decides when the walls can close.

Most of the time goes into things you won’t see in the finished room: waterproofing, curing, waiting for parts. Which seems unfair, until you remember it’s also why the shower doesn’t leak.

What really sets the schedule

Waterproofing. Membranes and mortar need time to cure before tile and grout go on. A contractor who skips the wait saves you a day now and costs you a ceiling later.
Shower glass. Custom glass is measured after the tile is up, then made to fit. That often takes a week or two, so buy a shower curtain for the meantime. You’ll feel silly. You’ll also be dry.
Special-order fixtures. If the vanity or faucet isn’t on the shelf, order it the day you choose it. The plan gives it four weeks; the catalogue may disagree.

Why not just do this in Excel?

Because the tiler will be two days late, and in a spreadsheet that means recolouring a row of cells for everything that comes after. In Gantton, tasks are linked, so moving one moves the rest, and weekends and holidays are skipped for you. (Gantt charts in Excel, compared.)

The plan as text

The same plan in plain text. Copy it and press Ctrl+V in Gantton, or paste it into ChatGPT, Claude or any AI assistant and ask it to fit the plan to your situation first. (More on that in plans from AI assistants.)

Plan: Bathroom renovation
Colours: Green = You, Orange = Contractor, Purple = Decisions and orders, Navy = Permits and inspections
- Planning
  - Measure the bathroom | 1d | green
  - Get contractor quotes | 2w | after Measure the bathroom | green
  - Hire the contractor | milestone | after Get contractor quotes | purple
  - Choose tile and fixtures | 1w | after Hire the contractor | purple
  - Vanity and fixtures delivered | 4w | after Choose tile and fixtures | purple
    > Special-order vanities and faucets can take a month or more. Ask before you fall in love with one.
  - Plumbing permit | 2w | after Hire the contractor | navy
- Demolition
  - Plan for the other bathroom | 1d | after Plumbing permit | green
    > Or make friends with a neighbour.
  - Demolition | 2d | after Plan for the other bathroom | orange
- Rough-ins
  - Plumbing rough-in | 2d | after Demolition | orange
  - Electrical and fan | 1d | after Demolition | orange
  - Rough-in inspection | milestone | after Plumbing rough-in, Electrical and fan | navy
- Walls and floor
  - Cement board and drywall | 2d | after Rough-in inspection | orange
  - Waterproofing | 2d | after Cement board and drywall | orange
    > Each coat needs time to cure. This is not the step to rush.
  - Floor and wall tile | 5d | after Waterproofing | orange
  - Grout and seal | 2d | after Floor and wall tile | orange
- Fixtures and finishing
  - Measure for shower glass | 1d | after Floor and wall tile | orange
  - Shower glass made | 2w | after Measure for shower glass | purple
  - Install vanity and toilet | 1d | after Grout and seal, Vanity and fixtures delivered | orange
  - Paint | 2d | after Install vanity and toilet | green
  - Install shower glass | 1d | after Shower glass made, Grout and seal | orange
  - Final plumbing inspection | milestone | after Paint, Install shower glass | navy
  - First uninterrupted shower | milestone | after Final plumbing inspection | green

More templates

One last tip: take photos of the open walls before they close. Future you, hunting for a pipe with a drill, will be grateful.