Templates › Software project

Software development project plan template

A free Gantt chart for building and releasing an app or a software feature. Agile purists may want to look away. Everyone else still has to tell someone when it’ll be done.

Wk 1 Wk 3 Wk 5 Wk 7 Wk 9 Wk 11 Wk 13 Wk 15 Wk 17 Wk 19 Define Requirements and user stories UX design Technical design Scope agreed Build Sprint 1 Sprint 2 Sprint 3 Automated tests Feature complete Test QA testing Bug fixing Beta release Fix beta issues Release Release notes and docs App store review Release Monitor and hotfix
ProductDesignDevelopmentTestingphasemilestone
Edit this plan in Gantton Opens as your own copy. No account, no signup, and it stays in your browser.

How long does a software project take?

This plan runs about 20 working weeks with three two-week sprints, which fits a modest app or a solid new feature. Add or remove sprints to match your scope. Gantton makes that easy: copy a sprint, paste it, and the rest of the plan moves out.

What really sets the schedule

Scope. The plan assumes the scope is agreed before the first sprint. It won’t entirely be. When something gets added, add a task for it, so the release date stays honest.
Testing and fixing. These get squeezed first when the build runs late, and they’re exactly the part users notice. Keep them as real tasks on the chart, not as “whatever time is left”.
Things you don’t control. App store reviews, security reviews and customer sign-offs all take time on someone else’s calendar. Put them on yours too.

Agile and Gantt charts

A Gantt chart doesn’t replace your sprint board; it sits above it. The board says what’s happening this week. The chart says when the whole thing lands, and what moves if sprint 2 runs long. Most stakeholders only ever ask the second question.

The plan as text

The same plan in plain text. Copy it and press Ctrl+V in Gantton, or paste it into ChatGPT, Claude or any AI assistant and ask it to fit the plan to your situation first. (More on that in plans from AI assistants.)

Plan: Software project
Colours: Purple = Product, Blue = Design, Orange = Development, Green = Testing
- Define
  - Requirements and user stories | 2w | purple
  - UX design | 2w | after Requirements and user stories | blue
  - Technical design | 1w | after Requirements and user stories | orange
  - Scope agreed | milestone | after UX design, Technical design | purple
- Build
  - Sprint 1 | 2w | after Scope agreed | orange
  - Sprint 2 | 2w | after Sprint 1 | orange
  - Sprint 3 | 2w | after Sprint 2 | orange
  - Automated tests | 6w | after Scope agreed | green
  - Feature complete | milestone | after Sprint 3, Automated tests | purple
- Test
  - QA testing | 2w | after Feature complete | green
  - Bug fixing | 2w | after QA testing | orange
  - Beta release | 2w | after Bug fixing | green
    > Real users find the bugs your testers were too sensible to cause.
  - Fix beta issues | 1w | after Beta release | orange
- Release
  - Release notes and docs | 1w | after Feature complete | purple
  - App store review | 1w | after Fix beta issues | purple
    > For mobile apps. Reviews often take a day or two, but leave room for a rejection.
  - Release | milestone | after App store review, Release notes and docs | purple
  - Monitor and hotfix | 2w | after Release | orange

More templates

One last tip: the last 10% of the work takes the second 90% of the time. Plan for the second 90%.