Website redesign project plan template
A free Gantt chart for a website redesign, from the kickoff meeting to the morning after launch. Built by someone who has sat through a lot of website projects, and noticed what they all have in common.
How long does a website redesign take?
This plan runs about 13 working weeks for a small-to-medium site. Larger sites take longer mostly because there’s more content to move and more people to approve it, not because the code is harder.
The milestones in purple are approvals. They take no time on the chart and, in real life, often more time than anything else. If your stakeholders are busy people, give each approval a few days of its own.
What really sets the schedule
Why not just do this in Excel?
Website projects slip in small ways: a review takes three days longer, the photographer reschedules. In a spreadsheet each slip means updating every date after it. In Gantton the tasks are linked, so the plan updates itself and the launch date tells you the truth. (More on Gantt charts in Excel.)
The plan as text
The same plan in plain text. Copy it and press Ctrl+V in Gantton, or paste it into ChatGPT, Claude or any AI assistant and ask it to fit the plan to your situation first. (More on that in plans from AI assistants.)
Plan: Website redesign
Colours: Purple = Client and approvals, Blue = Design, Green = Content, Orange = Development
- Discovery
- Kickoff meeting | milestone | purple
- Analytics and content audit | 1w | after Kickoff meeting | blue
- Stakeholder interviews | 1w | after Kickoff meeting | blue
- Goals and requirements | 3d | after Analytics and content audit, Stakeholder interviews | purple
- Structure
- Sitemap | 3d | after Goals and requirements | blue
- Wireframes | 2w | after Sitemap | blue
- Wireframes approved | milestone | after Wireframes | purple
- Design
- Visual design concepts | 2w | after Wireframes approved | blue
- Design approved | milestone | after Visual design concepts | purple
- Design the remaining pages | 2w | after Design approved | blue
- Content
- Content plan | 3d | after Sitemap | green
- Write and gather content | 5w | after Content plan | green
> The most underestimated task on any website project. Start it early and chase it often.
- Photos and images | 2w | after Content plan | green
- Build
- Set up the CMS | 1w | after Wireframes approved | orange
- Build page templates | 3w | after Design approved, Set up the CMS | orange
- Load the content | 1w | after Build page templates, Write and gather content, Photos and images | green
- Redirects from old pages | 2d | after Load the content | orange
> Skip this and every link to your old site breaks. Google notices. So do your customers.
- Launch
- Test on phones and browsers | 1w | after Load the content, Design the remaining pages | orange
- Fixes | 1w | after Test on phones and browsers | orange
- Final sign-off | milestone | after Fixes, Redirects from old pages | purple
- Go live | milestone | after Final sign-off | orange
- Post-launch checks | 1w | after Go live | orange
More templates
One last tip: launch on a Tuesday morning. Never a Friday afternoon. Nobody wants to spend the weekend fixing the contact form.