Garage and workshop building timeline template

A free Gantt chart for building a detached garage or a backyard workshop, from checking what your lot allows to moving the tools in. Most of the waiting happens before the first shovel. That’s normal.

Wk 1 Wk 3 Wk 5 Wk 7 Wk 9 Wk 11 Wk 13 Wk 15 Wk 17 Design and approvals Decide size and use Check zoning and setbacks Drawings Get contractor quotes Hire the contractor Building permit Site and foundation Utility locates Excavation Footing inspection Pour footings and slab Concrete cures Structure Framing Roof Windows and doors Garage door Framing inspection Services and finishing Electrical Electrical inspection Insulation and drywall Siding and trim Final inspection Move the tools in
YouContractorDecisions and ordersPermits and inspectionsphasemilestone
Edit this plan in Gantton Opens as your own copy. No account, no signup, and it stays in your browser.

How long does it take to build a garage or workshop?

This plan comes to about 19 working weeks with a smooth permit. The building is maybe half of it. The rest is finding out what you’re allowed to build, drawing it, and waiting for someone at the city to agree.

If your design needs a variance (a bit taller, a bit closer to the fence), add a few months for the hearing. Then decide whether the extra foot is worth it. Sometimes it is.

What really sets the schedule

Zoning. Every lot has limits on size, height and setbacks, and a detached building is where people bump into them. Check before you draw, not after.
Power. A workshop usually needs more power than a garage: a subpanel, 240-volt circuits, more outlets than seems reasonable. Decide early, because it changes the drawings, the permit and the trench.
Concrete. The slab needs time to cure before heavy framing loads go on it, and it really prefers not to freeze while it does. In a Canadian winter, this one task can rearrange the whole plan.

Why not just do this in Excel?

You could. But a permit that takes eight weeks instead of six pushes twenty tasks, and in Excel that’s twenty rows to fix by hand. In Gantton they’re linked, so one change moves them all, skipping weekends and holidays. (More on Gantt charts in Excel.)

The plan as text

The same plan in plain text. Copy it and press Ctrl+V in Gantton, or paste it into ChatGPT, Claude or any AI assistant and ask it to fit the plan to your situation first. (More on that in plans from AI assistants.)

Plan: Building a garage or workshop
Colours: Green = You, Orange = Contractor, Purple = Decisions and orders, Navy = Permits and inspections
- Design and approvals
  - Decide size and use | 1w | green
  - Check zoning and setbacks | 1w | after Decide size and use | navy
    > Lot coverage, height and distance from the property lines. Find out before you fall in love with the drawings.
  - Drawings | 2w | after Check zoning and setbacks | green
  - Get contractor quotes | 2w | after Drawings | green
  - Hire the contractor | milestone | after Get contractor quotes | purple
  - Building permit | 6w | after Drawings | navy
- Site and foundation
  - Utility locates | 1w | after Hire the contractor | navy
  - Excavation | 2d | after Building permit, Utility locates | orange
  - Footing inspection | milestone | after Excavation | navy
  - Pour footings and slab | 3d | after Footing inspection | orange
  - Concrete cures | 1w | after Pour footings and slab | orange
- Structure
  - Framing | 2w | after Concrete cures | orange
  - Roof | 1w | after Framing | orange
  - Windows and doors | 3d | after Roof | orange
  - Garage door | 1d | after Roof | orange
  - Framing inspection | milestone | after Windows and doors | navy
- Services and finishing
  - Electrical | 1w | after Framing inspection | orange
  - Electrical inspection | milestone | after Electrical | navy
  - Insulation and drywall | 2w | after Electrical inspection | orange
  - Siding and trim | 2w | after Framing inspection | orange
  - Final inspection | milestone | after Insulation and drywall, Siding and trim, Garage door | navy
  - Move the tools in | milestone | after Final inspection | green

More templates

One last tip: whatever size you drew, the tools will fill it. Draw it bigger.