Gantton Open Gantton

Templates › Building a deck

Deck building timeline template

A free Gantt chart for building a deck, whether you’re hiring it out or doing it yourself over too many weekends. Footings, framing, decking and railings, with the permit and inspections in the right places.

Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7 Wk 8 Design and approvals Measure and sketch the deck Choose materials Drawings for the permit Building permit Utility locates Order lumber and hardware Foundation Dig footing holes Footing inspection Pour footings Concrete cures Framing Ledger and beams Joists Framing inspection Decking and railings Lay the decking Stairs Railings Final inspection First barbecue
YouBuilderDecisions and ordersPermits and inspectionsphasemilestone
Edit this plan in Gantton Opens as your own copy. No account, no signup, and it stays in your browser.

How long does it take to build a deck?

This plan runs about 8 working weeks, and the building itself is only the last two or three. The rest is drawings, the permit, the locates and the concrete, which all happen before the deck looks like anything at all.

Doing it yourself? Each working day here is roughly a day for a crew. For one person with a borrowed mitre saw, it’s more like a weekend. Change the durations accordingly, and be honest.

What really sets the schedule

Utility locates. Before you dig, ask for the gas, power and cable lines to be marked. It’s free in most of Canada and the US, it’s the law in most places, and it can take a week or so to arrive. Book it the day you decide to build.
Footings. In cold climates, footings go below the frost line, which can be four feet down or more. Your building department will tell you the depth, and many will want to see the holes before you pour.
Weather. Concrete, stain and lumber all prefer dry days. Leave some slack in the plan, or accept that the barbecue may happen in a sweater.

Why not just do this in Excel?

Rain doesn’t care about your spreadsheet. When a wet week pushes the footings back, Gantton moves the framing, decking and railings after it, because they’re linked. In Excel, you move them. (More on Gantt charts in Excel.)

The plan as text

The same plan in plain text. Copy it and press Ctrl+V in Gantton, or paste it into ChatGPT, Claude or any AI assistant and ask it to fit the plan to your situation first. (More on that in plans from AI assistants.)

Plan: Building a deck
Colours: Green = You, Orange = Builder, Purple = Decisions and orders, Navy = Permits and inspections
- Design and approvals
  - Measure and sketch the deck | 2d | green
  - Choose materials | 3d | after Measure and sketch the deck | purple
  - Drawings for the permit | 1w | after Choose materials | green
  - Building permit | 3w | after Drawings for the permit | navy
  - Utility locates | 1w | after Measure and sketch the deck | navy
    > Free, required, and much cheaper than finding the gas line with a shovel.
  - Order lumber and hardware | 1w | after Choose materials | purple
- Foundation
  - Dig footing holes | 1d | after Building permit, Utility locates | orange
  - Footing inspection | milestone | after Dig footing holes | navy
  - Pour footings | 1d | after Footing inspection | orange
  - Concrete cures | 3d | after Pour footings | orange
- Framing
  - Ledger and beams | 2d | after Concrete cures, Order lumber and hardware | orange
  - Joists | 2d | after Ledger and beams | orange
  - Framing inspection | milestone | after Joists | navy
- Decking and railings
  - Lay the decking | 3d | after Framing inspection | orange
  - Stairs | 2d | after Lay the decking | orange
  - Railings | 2d | after Stairs | orange
  - Final inspection | milestone | after Railings | navy
  - First barbecue | milestone | after Final inspection | green

More templates

One last tip: buy a few extra deck boards. The one you need will be the one that split.